Sunoco Pipeline Construction Work Update

As part of the local pipeline construction work, Sunoco Pipeline is scheduled to complete welding and pipeline installation in the area of Gamble Lane and Judy Way in Aston Township.

Pullback activities are scheduled to start on Tuesday March 13th, 2018, and at least three night shifts are anticipated during this time to complete installation. This critical stage of pipe installation requires uninterrupted activity so that a successful result is achieved.

The schedule and duration is subject to change due to weather or other unforeseen circumstances. The activity will include lighting and truck traffic, welding, as well as movement and installation of pipe. Gamble lane will remain closed until the pullback work is completed.

Sunoco Pipeline has taken measures to avoid disruption: additional sound barriers have been erected at the site to mitigate noise, and lighting will be directed away from residences. This work is separate from our daytime drilling operations and requires around-the-clock shifts.

For any questions or concerns, please call Sunoco Pipeline’s 24-hour help line at (855) 430-4491.